Monday, March 15, 2010

1st course



The first course of Flexcrete is done! This course got the mortar joint underneath so required the extra step of mixing mortar.


This is the same short wall from the "Corners Post." As you can see, we cut a small block to fit the space.


Basically how things look at the moment. The first three courses have the most cutting and fitting to do because of all the electrical outlets. After that, I'm hoping the middle courses go faster.

Monday, January 25, 2010

Corners

It all starts with laying the corner blocks first.



The first course gets mortar underneath the block. This ends up being about 3/4". The shopvac was to clean any debris off the stemwall before applying the mortar. 





We use the level on top of every block. The tripod has a laser to make sure that every block is set at the same height. We can adjust the blocks on the first course due to the mortar joint underneath. After the first course, the blocks get a thinset which is a much thinner joint. This is why it is critical to get the first course right, any small error here gets magnified as we get higher.





Here are a couple of finished corners. 






Flexcrete Delivery

Well, we got our first two trucks of Flexcrete. 



This truck had 16 pallets on it, plus thinset. We unloaded down on the flat area you can see in the photo.






Here is the forklift we got to drive. It was ok, but the tractors are a lot funner.






It took about 45 minutes to unload the truck, but a couple of hours to get everything up the long driveway.






That is what it looks like with 32 pallets. 48 blocks per pallet = 1536 blocks. Each block is 8"x12"x24" and weighs about 54 pounds. Still more to come.