Monday, January 25, 2010

Plywood Floor

We have been very busy lately, which has made it hard to keep up with the blogging. We now have a plywood floor! This was a pretty fun job as we got to see a lot of progress as we went. Here are some photos.





Here we are in the beginning. We cut the boards to fit with a skilsaw, then applied glue to every joist. Once it is in place we screwed it down with approximately 32 screws per sheet. I'm guessing we used about 38 pounds of screws for the entire floor.



Here we are making sure the floor will come out flat and level. I am using a planer to take down a high joist. A couple of joists were low, we solved this by gluing a shim down before the plywood. Using the level and a string running from end to end you can get a very accurate measurement of anything that is high or low.





Here is a shot of the finished plywood floor. It came out great. Unfortunately we have had a lot of rain to deal with since this photo. Our original plan was to stain and seal the plywood and use it as our regular floor for awhile. We were not able to get a stain on in time, we have a sealer on it now. We will see how it goes, but by the time we get the walls up and the roof on, our floor will have taken a lot of abuse. It is possible we will still be able to finish it to look nice, but we might have to get a real floor sooner than we expected. 

Sunday, October 4, 2009

Floor



The lumber has arrived and we have been busy getting started on the floor.

Glulam beams on the far left in the wrapping. The shortest was 16' the longest 32'. Next pile over are the joists. Truss joists on the bottom, up from that are the 2"x10" and 2"x12" joists. The green pile is treated lumber for the ledgers, 3"x12" and 2"x12"


Two days to put all the Glulam beams in. Kristi operated the excavator and lifted them all into place. Every beam needs to be cut and shaped to fit. Holes need to be drilled for bolts.



The build team. We have hangers nailed on the beams. The ledger is still missing from the back wall, you can see it on the left. Some of the truss joists are in.